The Dover Planning Board granted two 1-year extensions for erosion and sediment control permits for Dover State and Roushiano properties. The board also discussed proposed changes to the town's zoning chapter, which will undergo a public hearing by the Town Board in late August.
About this meeting
- Government Body
- Planning Board
- Meeting Type
- Planning Board
- Location
- Dover, NY
- Meeting Date
- July 6, 2026
Transcript
63 sections
of time to February 1, 2013 to complete the work contemplated on the permit. And whereas second, and whereas third, and whereas fourth, and whereas fifth, and whereas sixth, and whereas seventh, and whereas eighth, and whereas ninth, and whereas 10th, 11th, 12th, 13th, 14th, 15th, 16th, 17th, 18th, 19th, 20th, 21st, 22nd, 23rd, 24th. OK. Whereas on June 17, 2025, the planning board granted the applicant a 24th extension of time to August 1 of 2026, this year. And whereas by letter dated May 18, 2026, the applicant has requested an additional extension of time to complete the work authorized under the permit. And whereas permit renewals are type 2 actions in secret. And I lost my place. I got to start over. And whereas by letter dated June 15, 2023, the applicant provided a confirmation that the cost estimates or the forms bond were still valid and the Department of Health approval has been extended through September 19, 2025. And whereas the planning board engineer has determined that the cost estimates from 2023 are valid through the requested extension period. And whereas the planning board has considered the particular circumstances of the applicant, which warrant an extension thereof. Now, therefore, be it resolved, the planning board hereby grants the applicant a 25th extension. See, and you're all like, why does he read everything? 25th extension of time to August 1, 2027, to complete the work contemplated under the erosion settlement control permit as shown on the approved plan entitled Dover State, Town of Dover, Sheets 1-14, dated 10-21-04. Last revised, 6-11, prepared by Northern Westchester Civil Engineering, PC, subject to the satisfaction of the conditions set forth in a resolution adopted by the board on August 1, 2011. subject to the following conditions one within 30 days of this resolution confirmation that all fees and escrow have been paid failure to satisfy the condition will automatically avoid this extension two and 30 days resolution the confirmation that the required performance guarantee sixteen thousand four hundred five dollars will remain in full force in effect until at least august one twenty twenty seven failure to satisfy this condition will automatically avoid this extension three within thirty days of this resolution confirmation that dutch county department of health approval has been extended and is in effect before the results that before the authorized official may issue a to get compliance. Well, we're here shall provide the authorized official with a written statement indicating that all work authorizing the permit has been completed in accordance with the approved permit. This resolution is being offered by so was a lot of second by a member over here. Session. No discussion. Resolution granting extension of emergency center control permit approval Dover State subdivision. Secretary, please call the roll.
Member Williams.
Aye. Member Villano. Aye. Member Palmer.
Aye. Member LaRoberty. Aye. Chairman Quartin.
Aye. Resolution is adopted 5-0 with one absence. Next on the agenda. is Roushiano, Erosion and Sediment Control. A resolution granting extension of Erosion and Sediment Control permit approval. Roushiano, Erosion and Sediment Control permit for 236 and 246 Cricket Hill Road.
How are you doing?
Good?
Are you? Well, this is the material from right over states that you know we want to do some grading on this property.
One kind of with the other yes. Nothing's changed in the last 25 really 11 starts the other will start in the correct. And you're a burger and a winner to go down.
No comments.
They both said no comments. Senator Politello. No comments. Resolute Planning Board, comments, questions? No, okay.
Resolution granting extension of Erosion Center Control permit approval of Luciano Erosion Center Control Permit.
For again, this is just clear 236 246 cricket road Whereas on February 1 2010 the planning board granted the applicant Peter Roushiano and erosion signal control permit for disturbance has shown on the plan and title proposed fill plan Roushiano property prepared by John Mayer consulting PC dated 7 7 2009 last revised 1 6 2010 to expire on February 2 2011 subject to several conditions including submission of Florence guarantee in the amount of $3,000 And whereas on October 4, 2010, the planning board granted the applicant a six-month extension of time to August 2, 2011 to complete the work contemplated on the permit. And whereas second, whereas third, fourth, fifth, sixth, seventh, eighth, ninth, tenth, eleventh, twelfth, thirteenth, fourteenth, fifteenth, sixteenth, 17th 18th 19th 20th 21st 22nd 23rd 24th 25th 26th 27th wait okay and whereas on June 16, 2025, the planning board granted the applicant a 27th extension of time to August 2nd, 2026, which is this year, to complete the work, contemplate another permit, and whereas by letter dated May 18, 2026, the applicant has requested an additional extension of time to complete the work, and whereas pursuant to section 65-8K of the code, PLANNING BOARD MAY GRANT AN EXTENSION OF TIME TO COMPLETE THE WORK CONTEMPLATED UNDER AN EROSION SENTENCING CONTROL PERMIT IF IN ITS INSCRUCTION THE PLANNING BOARD FINDS THAT SUCH EXTENSION IS WARRANTED EMERGENCY PERMIT RENEWALS ARE TYPE 2 ACTIONS UNDER SECRA AND WHEREAS BY LETTER DATED JUNE 15 2023 THE APPLICANT PROVIDED A CONFIRMATION OF THE COST ESTIMATES FOR THE RUSSIANO PERFORMANCE BOND We're still valid and whereas for the playing board engineer has determined that the bond estimates provided in 2023 are valid for the required extension period and whereas the playing board has considered particular circumstances of the applicant which warrant an extension thereof. now therefore be resolved the planning board here by grants the applicant a one-year extension of time to august 2nd 2027 to complete the work contemplated under the erosion settlement control permit as shown on the approved plan entitled proposed fill plan russian property prepared by john mayer consulting pc 7 2009 as last revised subject to the following conditions one within 30 days of this resolution conformational fees and escrow have been paid failure to satisfy this condition will automatically void the extension this extension two within the 30 days of this resolution confirmation that required forms guarantee three thousand dollars will remain in full force in effect until at least august 2nd 2027 failure to satisfy this condition will automatically avoid this extension be further resolved that the before the authorized official may issue a certificate of compliance the planning board engineer shall provide The authorized official with a written statement indicating that all work authorizing the permit has been completed in accordance with the approved permit. This resolution being offered by. Number of lotto second by I can number Palmer discussion. Seeing no discussion. Resolution granting extension of erosion center control permit approval Russian erosion and sediment control permit Again, this is for 236 246 curricular Road Secretary please call the roll never Williams.
I never Milano never Palmer.
All right That's not the dice keep going I
Chairman courting I resolution is adopted for 0 with 2 absences. So okay, thank you have a good day next year. All right next. They said Belgium scored so all right. Session update of town of Dover zoning chapter one 45.
So the proposed zoning map the map hasn't changed since the last edition Because that the map changes were approved in when that was the map that was presented like a 24 22 22 January So no changes All right
All right and then there is a revised chapter one 45 zoning. It is a 123 pages. And I will read it aloud now. No.
No, you're not.
All right. Secretary Van Millen, so the town board is looking to adopt this when? They're meeting they're meeting at the end of July of a meeting at the end of August.
I believe the way it looks that they're going to have a public hearing on it at the end of August and a probably adopted said hopefully September. So any comments that this board may have should either come to the town clerk or myself and we'll give it to the board.
Yeah. Yeah. And if the playing board wishes to send something formally along, we could do that in a meeting in August. That'll be sufficient time, you're saying?
Oh, yeah.
Okay.
I believe when I spoke to Supervisor, you know, he said he was going to open for comments until written comments to August 15th. And then the public hearing would be the end of August, so everything would compile.
Okay.
That can change.
Sure, sure, sure.
But if anyone wants a hard copy, either contact me or Nicole.
Bring a ring of paper.
Get it for you.
Is there one thing that's going to be important for this board? Is there a provision either in the local law that adopts this or this chapter that talks about what happens to projects that are in progress? There's some kind of grandfathering clause that allow you should there is yeah.
Yeah Yeah, I mean there's a number of Projects in progress. I know one thing that was discussed at one point was getting rid of having 20-something extensions and
Yeah, that's kind of being under the erosion and sediment control when we hit that.
Right. So whether Mr. Ruggiano will get grandfathered, I guess he would?
That, I don't think so.
Well, it's not up to you or I, but whatever the law says, I guess.
That's got to be one of the major discussions with us when we do erosion and sediment control.
If he had a big grandfather, it could change significantly the variances that he needs.
Sure.
How extensive are these changes?
Most of the changes are under the use table. If you notice the use table, it was like one page long. Now it's almost like two pages long.
Are the changes highlighted?
No, they did not highlight them. I know Dutchess County has already received it and they've asked for a red line version and I did ask Richie Renia if we could get a copy of that and if I get that, I'll let you know. In major changes are under where would be the plant community Food trucks Short-term rental there's a whole section that they're all one right after the other and I think that's one of the major changes I Some of the changes are like there's a residential uses multifamily dwelling is there but you can't no more conversion to multifamily right.
There are a few things that the board had reserved for itself. It looks like the only thing remaining I was soil mining.
And I think what's happened over the last, I know for me, the last five years is every time someone goes to the building department, we have to figure out whether it's a service business or a retail business not listed elsewhere. And that listed elsewhere list gets longer and longer every year. So a lot of that's been added, like art gallery, brew pub, commercial wood processing is new.
Yeah, I'm just saying relevant to the... Let me go back. One of the things that'd be relevant to the planning board is that the... Come on. So right now, under the use table, designates a use permitted by special permit issued by the town board would be adult entertainment, communication tower, junkyard, soil mining, and those first three, not soil mining, would go to the planning board. Not that it comes up often or at all, but it just, you know, those three, adult entertainment, communication tower, and junkyard would come to the, Would come to the planning board not the town board I Haven't looked I haven't had a chance to really read through it fully. I know there's also a provision That you know anything that's like not expressly Permitted but not actually denied is a special permit of the town board. I don't know if that's still and they're like that anymore Okay Yeah. So, you know, it's something certainly to read through because it's, you know, something that the town and the planning board specifically are going to have to live with for the next five years, 20 years, you know, whatever it is.
I have a feeling that this committee is going to be ongoing for a very long time.
Yeah. No, it'd be good to make, you know, adjustments as things come up, you know, like what happened with solar, you know, solar law and other things. So, yeah.
And you know, we've also said if any member of a board wants to come in to one of the meetings, just let me know, and I would let the chairman know. And so this way, you know, if they're coming, if we cancel, we can tell them we're not gonna meet this month. But we meet the third Wednesday of every month. at 5 o'clock.
Yeah. So again, if you have anything that you want to express individually, you're certainly welcome to do that. If we as the planning board wish to do that, we're certainly welcome to do that. The only catch there is that our retainer does not include The retainer agreement we have with our attorney does not include review of legislation. So Attorney Palladaro can't really get deep into anything on any of this.
And the Zoning Update Committee has its own planner.
Right. Right. So anyway, so just read through it if, you know, if the planning board, if members of the planning board do wish to, you know, say this is a, you know, this is what the planning board thinks about this, then that's something that, you know, please send an email sometime in July so it could be considered sometime in August. That way, you know, it's within the deadlines that the town board has. And like I said, if you have any, you know, individual concerns Thoughts feelings questions concerns you can certainly get them to the the town board the planning board will not be having a Our own public hearing on this that's not our role in this so anybody hearing this you wouldn't come to the planning board with your thoughts About this proposed zoning and That should go to the town board and as secretary Van Millen stated they will be having a public hearing regarding that so Anything further to discuss Yeah, but I do I do agree with this I No, it's great. I mean, definitely needed. I think, you know, everything I've heard makes sense. I haven't read every word yet, but, you know. So, but I agree with Member Villano. rather than having to read through a 100 something pages because look at these are the additions. These are the deletions whatever change.
Yeah, the red line version.
So I think everyone would benefit from that. So that would be certainly my comment back to.
So I did have a red light version that was for versions.
Sure right. Yeah, thank you.
Yeah, really it might be a little hard to go back to that. Thank you.
Thank you for all your work. All right. So, any further discussion? All right. Seeing no further discussion on this. And our next scheduled meeting is 2 weeks from tonight July 20th of the deadline for that has passed. There's a public hearing scheduled for July 20. Do him was there anything else then that we're expecting. Well possibly likely like it was something. Something else but I can't remember something else OK. And then the meeting after that is August 3rd with the deadline of July 15th.
Any further business before the planning board?
Okay, so you know for the business, I'll make a motion to adjourn. Seconded by? Again. Member Palmer. All those in favor of adjourn say aye.
Aye.
Aye. We're adjourned.