Planning Commission - Regular Meeting

Tuesday, August 4, 2026Official site

The Washoe County Planning Commission approved a partial abandonment of a 30-foot bridle path easement, reducing it to 15 feet, and approved a special use permit for a 450 MW solar electric generating facility. Additionally, a common open space tentative subdivision map and special use permit for Silverado Village at Eagle Canyon – Phase 3, a senior housing development, were approved.

About this meeting

Government Body
Planning Commission
Meeting Type
Planning Commission
Location
Washoe County, NV
Meeting Date
August 4, 2026

Published excerpts

Only published remarks appear here. The full transcript is not published.

No published remarks yet

These excerpts are remarks by officials whose identity a person confirmed, from a transcript generated automatically from the official public meeting video and presented unedited. Accuracy may vary; view the original recording for reference.