CHAIR CALLS MEETING TO ORDER

CHAIR CALLS MEETING TO ORDER

PLEDGE OF ALLEGIANCE TO THE FLAG

PLEDGE OF ALLEGIANCE TO THE FLAG

ROLL CALL

ROLL CALL

PUBLIC COMMENT

PUBLIC COMMENT

Audience participation is encouraged. Public comments are limited to 3 minutes.

COMMUNICATIONSItem 2

Declaration of conflicts of interest on any agenda items (Board of Public Utilities)

CONSENT CALENDARItem 3

Minutes of August 24, 2026

CONSENT CALENDARItem 4

Excuse absence of Board Member Wright from August 10, 2026, Board of Public Utilities meeting

CONSENT CALENDARItem 5

Recommend City Council approve Assignment and Assumption Agreement for (1) Request for Proposal 2137 with Resource Innovations, Inc., formerly Richard Heath & Associates, Inc., for $5,000,000 for Outdoor Lighting Program for term effective January 13, 2023, to January 13, 2027; and (2) Request for Proposal 2139 with Resource Innovations, Inc., formerly Richard Heath & Associates, Inc., for $5,000,000 for Small Business Direct Installation Program for term effective January 23, 2023, to January 23, 2027

CONSENT CALENDARItem 6

Recommend City Council approve Agreement with Southern California gas Company (SoCal Gas) for Conveyance of Easements for portion of City-owned land, identified as Assessor's Parcel Numbers 155-070-031, 163-300-014 and 189-120-001, located at Riverside's Regional Water Quality Control Plant (RWQCP) and (Riverside Energy Resource Center ) RERC facilities

CONSENT CALENDARItem 7

Approve Work Order 2701874 for total capital expenditure of $72,000 from Electric Fund Public Utilities City-wide Communications Network Capital Account to re-route existing fiber optic cable at Orange Street cross-connect cabinet to support Hunter circuits 21 and 22 4kV-12kV Conversion Project

CONSENT CALENDARItem 8

Receive update on upcoming gas turbine repairs on Unit 2 at Riverside Energy Resource Center

CONSENT CALENDARItem 9

Approve Work Order 2623663 for total capital expenditure of $104,000 from Electric Fund Public Utilities City-wide Communications Network Capital Account for fiber installation to Rohr Substation

CONSENT CALENDARItem 10

Authorize additional change order authority for Bid 8172 to Doty Bros. Equipment Company, Norwalk, for not-to-exceed $883.47 from Public Utilities Electric Capital Account for Merrill Avenue Transformer P753 Upgrade Project

Approve additional funding for Work Order 2514460 for $883.47 for revised total capital expenditure of $120,883.47 for design, construction, construction support, contract administration, inspection and construction change order authority for Merrill Avenue Transformer P753 Upgrade Project

CONSENT CALENDARItem 11

Approve Agreement for Quote VRN 123674-006 through Omnia Partners Cooperative Agreement R250307 with Vector Resources, Inc., Rancho Cucamonga, for $50,417 from Electric Fund Public Utilities Building and Improvements Account for Mission Square Camera Upgrade Project

DISCUSSION CALENDARItem 12

Receive update on City of Riverside's use of allowance value and proceeds from sale of Greenhouse Gas Allowances in 2025 and preliminary update on new Cap-and-Invest regulations

DISCUSSION CALENDARItem 13

Recommend City Council approve Cost Sharing Agreement with San Bernardino Valley Municipal Water District for $29,405 from Water Fund Public Utilities Water Engineering Professional Services Account

Approve expenditure of Riverside Public Utilities participation in The Salt and Nutrient Management Plan Phase 3A Study for $29,405 for Upper Santa Ana River Watershed Groundwater Basins

DISCUSSION CALENDARItem 14

Approve Agreement with ZENON Environmental Corporation (Veolia Water Technologies & Solutions) Oakville, Ontario, Canada, for $1,902,838 and authorize 10 percent change order authority for $190,284 for membrane replacement at John W. North Water Treatment Plant

Approve capital expenditure for Work Order 2703946 for $2,133,122 from Public Utilities Water Fund Facility Rehabilitation Account which includes services and change order authority costs for membrane replacement at John W. North Water Treatment Plant

BOARD MEMBER/STAFF COMMUNICATIONSItem 15

Systematic reporting on meetings, conferences, and seminars attended by Board members and/or staff

BOARD MEMBER/STAFF COMMUNICATIONSItem 16

Items for future Board of Public Utilities consideration as requested by members of the Board.

Only items that fall within the powers and duties of the Board of Public Utilities as set forth in the City Charter and/or the Riverside Municipal Code will be agendized for future discussion.

GENERAL MANAGER'S REPORTItem 17

Board Member Request List from Minute Order- August 2024 to July 2026

GENERAL MANAGER'S REPORTItem 18

Financial Results and Electric and Water Accounts Receivable and Delinquencies as of May 31, 2026

GENERAL MANAGER'S REPORTItem 19

Power Supply Report - June 2026

GENERAL MANAGER'S REPORTItem 20

WA-12 Agricultural Service Water Rate report as of July 31, 2026

GENERAL MANAGER'S REPORTItem 21

Water Contractor Panel updates for July 2026

GENERAL MANAGER'S REPORTItem 22

Water Supply Report - July 31, 2026

GENERAL MANAGER'S REPORTItem 23

Customer Engagement Report updates through July 2026