Board of Public Works - Regular Meeting

Tuesday, June 2, 2026

The Board of Public Works approved minutes, authorized the disposal of surplus IT property, and approved two change orders for water infrastructure projects. The board also approved claims totaling over $3.7 million across various departments.

About this meeting

Government Body
Board of Public Works
Meeting Type
Board Of Public Works
Location
Anderson, IN
Meeting Date
June 2, 2026

Transcript

23 sections

0:07Speaker 6

Nice of you to be here on time.

0:12 – 0:25Speaker 4

At this time, I'll call the regular Board of Public Works meeting to order. June 2nd, 2026 at 1.30 p.m. Let the record reflect what we have for Mr. Sims and myself for present. And with that, we're ready for approval.

0:26Speaker 3

I make a motion we approve the minutes as written.

0:29Speaker 4

Second. Are there any corrections? Hearing none, all those in favor signify by saying aye. Aye. So approved. Next, new business, controller.

0:38 – 0:57Speaker 6

Yes, sir. Thank you, Mr. Chairman. You have in front of you a list of surplus property put together by the IT department, old computer and peripheral items that are minimal value and just require disposal per the Indiana code you have on the document.

0:59Speaker 3

I make a motion we dispose of the surplus property.

1:04Speaker 4

Declare it.

1:05Speaker 3

Declare the disposal of the surplus property.

1:09Speaker 4

Second. Are there any questions? Hearing none, all those in favor, signify by saying aye. Aye. So approved. Hunter Department.

1:19 – 1:38Speaker 5

Thank you, Mr. Chairman. Members of the Board, we have a four-year request to approve change order number five for Division 3 well and raw water main project. Change order is a result of inadequate valving on existing raw water main. It contains significant drainage and cleanup, which would result in a delay in the project. The final cost for the change order is $20,132.

1:39Speaker 3

I make a motion we approve the change order 5 for Division Well and Ross Water Main Project.

1:48Speaker 4

Second. Are there any questions? Hearing none, all in favor signify by saying aye.

1:56 – 2:15Speaker 5

Mr. Chair, members of the board, you had before you a request to approve change order number three for Lafayette Treatment Plant Expansion Project. The change order encompasses a balance of final quantities minus additional construction costs and materials to avoid conflicts. The final cost for change order is a reduction of $36,540. That's the kind of life.

2:16Speaker 3

Me too. I'll make a motion we approve the change order for the Lafayette Treatment Plant Expansion Project. Second.

2:24Speaker 4

Any questions?

2:25Speaker 2

How close are they to finishing that project?

2:28Speaker 5

About a month.

2:30Speaker 2

That's the one that expands in there, right? That's the expansion.

2:32Speaker 5

Are they done on that Miserable property? Is that all done? Yes.

2:37 – 3:17Speaker 4

We're going to cross it around, yes. All in favor signify by saying aye. Aye. Aye. So approved. All business done. Approval of claims? Civil City, $1,983,883.99. Light and Power, $949,426.17. Water Department, $408,980.73. Water Pollution Control, $398,817.61. Stormwater, $54,919.94 for a grand total of three main, $796,028.44. I make a motion we pay the bills. Second. Any questions? Yeah. Do you know all those in favor, signify by saying aye? Aye.

3:18Speaker 3

I make a motion we...