City Commission - workshop
Tuesday, August 11, 2026
The City Commission received an update on the Tremont Barrel Fill site remediation, with the EPA conditionally approving the 95% remedial design report. Site preparation activities are expected to begin in mid-September, with drum removal potentially starting as early as December.
About this meeting
- Government Body
- City Commission
- Meeting Type
- City Commission
- Location
- Springfield, OH
- Meeting Date
- August 11, 2026
Published excerpts
Only published remarks appear here. The full transcript is not published.
No published remarks yet
These excerpts are remarks by officials whose identity a person confirmed, from a transcript generated automatically from the official public meeting video and presented unedited. Accuracy may vary; view the original recording for reference.